top of page

CERL self-assessment tool

Commercial Engagement Readiness Level (CERL)

The Commercial Engagement Readiness Level (CERL) framework describes how far a sustainable aviation fuel (SAF) project has actually progressed toward commercial operation. Where the CAAFI Fuel Readiness Level (FRL) and Feedstock Readiness Level (FSRL) tools track the maturity of the fuel and its feedstock, CERL looks more broadly at the project as a whole — across six dimensions, each a ladder of ten milestones arranged in the order projects normally reach them.

​

A project scores each dimension by the number of milestones it has completed in sequence, for a combined CERL score out of 60. The six measurement parameters are:

​

Fuel Readiness Level (FRL) · Feedstock Offtake Readiness Level (FORL) · Engineering Readiness Level (ERL) · Finance Readiness Level (F$RL) · Offtake Agreement(s) Readiness Level (OARL) · Execution Progression Completion Level (EPCL)

​

A companion self-assessment tool, the CERL Readiness Check, lets a project team score itself against the six ladders and produce a report. It runs entirely in the browser; nothing entered is stored or transmitted, and results are self-reported and unverified.

​

The ten ladder steps for each of the six parameters are listed below.

The six parameters and their ladder steps

01

Fuel Readiness Level (FRL)

  1. Basic SAF blending-component production principles observed and reported (pathway definition established)

  2. Tier alpha and beta prescreening completed; technical approach defined, enabling D4054 entrance

  3. Proof-of-concept production (500 ml) with analysis of multiple fuel samples

  4. Engagement with OEMs to initiate the D4054 process; market survey for cooperative research report

  5. Lab/bench: 100 liters produced

  6. Pilot completed

  7. Demo / full-scale technology evaluation completed; scaling analysis substantiated

  8. ASTM Tier 1 Research Report completed

  9. ASTM Tier 2 / Final Research Report completed (if applicable)

  10. ASTM qualification

02

Feedstock Offtake Readiness Level (FORL)

  1. Reviewed FSRL and/or have a plan for maturing the feedstock

  2. Risk/cost analysis for feedstock availability

  3. Risk/cost analysis for feedstock storage and transport

  4. Feedstock sustainability assessment and certification complete

  5. Feedstock qualifies for incentives (federal, state, local)

  6. Request for Information (RFI) complete

  7. Request for Proposal (RFP) complete

  8. Feedstock contract signed by both parties

  9. Feedstock supply assessments ready to share with SAF offtakers

  10. Initial feedstock, matching prior FRL work, delivered to staging site

03

Engineering Readiness Level (ERL)

  1. Regulatory and community engagement on site selection

  2. Scale-up potential known

  3. Site selection complete

  4. EPC vendor selected and provided with pilot & demo plant data

  5. Preliminary development schedule complete

  6. Front End Loading stage 1 (FEL-1) complete

  7. Front End Loading stage 2 (FEL-2) complete

  8. Pre-FEED complete

  9. Front End Engineering Design (FEED) complete

  10. Technically-based Authorization to Proceed (ATP) achieved

04

Finance Readiness Level (F$RL)

  1. People plan completed

  2. Funding plan completed

  3. ESG (environmental, social and governance) plan and targets defined

  4. Proforma (financial model) complete

  5. Seed funding obtained

  6. Preliminary construction timeline completed

  7. Competitive/strategic and intellectual-property (IP) analysis complete

  8. Debt holders identified

  9. Equity holders identified

  10. Final Investment Decision (FID)

05

Offtake Agreement(s) Readiness Level (OARL)

  1. Preliminary cost of production (COP) determined; life-cycle assessment (LCA)

  2. Number of offtakes needed to close the business case is known

  3. Pitched the opportunity to a potential offtaker

  4. Memorandum of Understanding (MOU) or other soft/non-binding agreement signed

  5. Detailed COP waterfall chart prepared

  6. Entered Heads of Terms (HoT) negotiations

  7. Confirmed with equity and debt holders that HoT clauses provide sufficient bankability

  8. Heads of Terms signed by all parties needed

  9. Binding offtake negotiations commenced

  10. Binding offtake agreement signed by both parties

06

Execution Progression Completion Level (EPCL

  1. Project approval (e.g., NEPA), including Environmental Impact Statement and Impact Assessment

  2. Project permits (water, building, communication, logistics)

  3. Groundbreaking

  4. Construction initiation

  5. Construction in process

  6. Construction completion

  7. Commissioning (handover from EPC contractor to operator)

  8. Operations start-up

  9. First fuel delivery

  10. Continuous operations (one year)

Need more details? Contact us:

We are here to assist. Contact us by phone, email or via our social media channels.

  • LinkedIn

© 2026 by Commercial Aviation Alternative Fuels Initiative

bottom of page